Currently, significant progress is being made on the milestones of the project.
by Patricia Schallert
The main outfall pipe from Marina Park is now installed underneath the Ventura Harbor and also installed out to sea (about 4,500 feet offshore), though there is still a lot more to do from now until Memorial Day. Trenching has already begun on Anchors Way from the Water’s Edge restaurant area.
However, there is still work to be done to finalize connections at Marina Park, which is expected to be completed by Memorial Day. Trenching has commenced on Anchors Way, starting from the Water’s Edge restaurant area. The trenching process is led by Blois Construction, who are responsible for installing the outfall pipe on Anchors Way, Schooner Drive, then on Harbor Blvd.
The pipe segments will be fused/welded together in 500-ft long sections along the street. Construction progresses in 500-feet increments, with each 500-foot segment taking several days to dig and shore up. Once the pipe is pulled into place, it is welded at the far end, connecting it to the already installed pipeline. Then, the trench is backfilled and paved. This process will be repeated several times on Anchors Way, and again on Schooner, with each 500-foot section taking approximately two to three weeks for completion.
According to Steve Mimiaga, the City’s construction manager, two 500-foot sections will be worked on along the eastbound (outbound) side of Schooner Dr., with an expected completion date of late April to early May. Then, trenching will begin on the southbound side of Harbor Blvd, close to the median, continuing under Spinnaker Dr. then turning into the City’s water reclamation facility (VWRF) about 800 ft south of the Spinnaker intersection. Throughout this process, traffic will remain open, although occasional and temporary lane closures may occur with the guidance of flagmen.
Construction is currently progressing according to the planned timeline, and it is anticipated that work in Marina Park will be completed before the Memorial Day weekend. The 24-foot tall soundwall within Marina Park is anticipated to be dismantled in March and replaced by contractor fencing. The area will be restored to its original appearance, with new mounds, grass, and an underground irrigation system completed, all scheduled to hopefully wrap up by Memorial Day weekend.
Learn more at the project website at www.cityofventura.ca.gov/OceanOutfall
Hotline for questions 805-500-8103